A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal have been completed. How many more men must be employed to finish the work in time?
Length of canal =6 km
In 20 days canal made =2 km
Remaining length of canal =6−2=4 km
Remaining time =35−20=15 days
In 20 days 2 km canal is made by =90 men
In 1 day 2 km canal is made by =90×20 men [Inverse relation between no. of days and people required ]
In 15 days 2 km canal is made by =90×2015 men
In 15 days 1 km canal is made by =90×2015×2 men
In 15 days 4 km canal is made by
=90×20×415×2 men =6×10×4 men
=240 men
∴ Number of more men to be employed to finish the work in time =240−90=150 men.