Question

A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal have been completed. How many more men must be employed to finish the work in time?

Open in App
Solution

Length of canal =6 km

In 20 days canal made =2 km

Remaining length of canal =62=4 km

Remaining time =3520=15 days

In 20 days 2 km canal is made by =90 men

In 1 day 2 km canal is made by =90×20 men [Inverse relation between no. of days and people required ]

In 15 days 2 km canal is made by =90×2015 men

In 15 days 1 km canal is made by =90×2015×2 men

In 15 days 4 km canal is made by

=90×20×415×2 men =6×10×4 men

=240 men

Number of more men to be employed to finish the work in time =24090=150 men.


flag
Suggest Corrections
thumbs-up
36
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon