A contractor undertook to complete a project in 90 days and employed 60 men on it. After 60 days, he found that 34 of the work has already been completed. How many men can he discharge so that the project may be completed on time ?
A
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
20
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
25
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
30
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 20
34th of the work is completed by 60 men in 60 days 34 of the work is completed by 1 man in (60 x 60) days
∴ The whole work will be completed 1 man in (60×60×43) days
Let the number of men who can complete the remaining 14 of the work in remaining 30 days be x.
Then, 14th of the work will be completed by x men in 30 days.
14th of the work will be completed by 1 man in (30x) days
∴ The work will be completed by 1 man in (X x 30 x 4) days