wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A fill having a volume of 1,50,000 cum is to be constructed at a void ratio of 0.8. The borrow pit soil has a void ratio of 1.4. The volume of soil required (in cubic meters) to be excavated from the borrow pit will be

A
1, 87, 000
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2,00,000
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
2,10,000
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2,50,000
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 2,00,000
(b)
The volume of soil solids from borrow pit soil and from fill should be equated.

Vs=V11+e1=V21+e

V1=V2×1+e11+e2

=150000×1+1.41+0.8

=2,00,000m3


flag
Suggest Corrections
thumbs-up
8
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Borrow Pit and Fill
SOIL MECHANICS
Watch in App
Join BYJU'S Learning Program
CrossIcon