A fill having volume of 150000m3 is to be constructed at a void ratio of 0.8. The borrow pit solid has a void ratio of 1.4. The volume of soil required to be excavated from the borrow pit will be
(Vs)fill=(Vs)Borrowpit
(VT1+e)fill=(VT1+e)Borrowpit
1500001+0.8×2.4=200000m3