wiz-icon
MyQuestionIcon
MyQuestionIcon
10
You visited us 10 times! Enjoying our articles? Unlock Full Access!
Question

A group of 48 workers can complete a piece of work in 11 days. But 48 workers worked on first day, 44 workers worked on second day, 40 workers worked on third day and so on. Unfortunately, on the 10th day, they had to restart the entire work . Then, find the time taken by the remaining workers to complete the entire work.


A

40 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

44 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

48 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

68 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B

44 days


Number of workers left on 10th day
= 48 + (10 - 1)(-4)
[ a = 48, d = -4]
= 48 + 9 × (-4)
= 48 - 36 = 12
Now, work done by 48 workers in 1 day =111
Work done by 1 worker in 1 day =111×48
Work done by 12 workers in 1 day =1211×48=144
Then, time taken by the remaining workers to complete the entire work, is 44 days.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Arithmetic Sequence
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon