A group of workers can do a piece of work in 24 days. However as 7 of them were absent it took 30 days to complete work. How many people actually worked on the job to complete it?
A
28
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
35
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
42
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A28 Let the original number of workers in the group be "x" therefore, actual number of workers =x−7. We know that the number of man hours required to do the job is the same in both the cases. Therefore, x(24)=(x−7).30 ⟹24x=30x−210 ⟹6x=210 ⟹x=35. Therefore, the actual number of workers who worked to complete the job =x−7=35−7=28.