A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job . if 6 men. leave after working for 6 days?
A
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
24 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is D 12 days 12 men can complete in 12 days 1 work 1 man can complete in 1 day 112×12 part of the work ∴ men can complete in 6 days 6×612×12 part of the work = 14th of the work Number of remaining men = 6 Remaining work = 34∵ 12 men can complete 1 work in 12 days 6 men can complete 34 work in 12×12×36×4=18 days ∴ Number of extra days = 18 - 6 = 12 days