A machine shop processes custom orders from variety of clients. A machining centre in a job shop for a local manufacturing company has five unprocessed jobs remaining at a particular point in time. The jobs are labeled J1,J2,J3,J4 and J5 in the order they entered the shop. The respective processing times and due dates are given in the table below:
Job | Processing time (in days) |
Due date (in days) |
J1 | 13 | 65 |
J2 | 32 | 48 |
J3 | 34 | 34 |
J4 | 4 | 36 |
J5 | 5 | 35 |
Job (J) |
Processing time (tj) |
Flow time (fj) |
Due date (dJ) |
Lateness (LJ) |
Tardiness (TJ) |
J4 | 4 | 4 | 36 | -32 | 0 |
J5 | 5 | 9 | 35 | -26 | 0 |
J1 | 13 | 22 | 65 | -43 | 0 |
J2 | 32 | 54 | 48 | 6 | 6 |
J3 | 34 | 88 | 34 | 54 | 54 |
∑FJ=177 | ∑TJ=60 |