Question

Five jobs (J1, J2, J3, J4 and J5) need to be processed in a factory. Each job can be assigned to any of the five different machines (M1, M2, M3, M4 and M5). The time durations taken (in minutes) by the machines for each of the jobs, are given in the table. However, each job is assigned to a specific machine in such a way that the total processing time is minimum. The total processing time is minutes.
M1 M2 M3 M4 M5
J1 40 30 50 50 58
J2 26 38 60 26 38
J3 40 34 28 24 30
J4 28 40 40 32 48
J5 28 32 38 22 44

  1. 146

Open in App
Solution

The correct option is A 146
M1 M2 M3 M4 M5
J1 40 30 50 50 58
J2 26 38 60 26 38
J3 40 34 28 24 30
J4 28 40 40 32 48
J5 28 32 38 22 44

Subtracting minimum value of each row from corresponding row elements.
M1 M2 M3 M4 M5
J1 10 0 20 20 28
J2 0 12 34 0 12
J3 16 10 4 0 6
J4 0 12 12 4 20
J5 6 10 16 0 22


Subtracting minimum value of each column from corresponding column.



Now Number of assignments is less than the number of machines. Hence current solution is not optimal. Now adding minimum uncovered value at all junctions and subtracting from uncovered values.



Hence,

Job 1 Machine 2

Job 2 Machine 5

Job 3 Machine 3

Job 4 Machine 1

Job 5 Machine 4

Total time = 30 + 38 + 28 + 28 + 22 = 146

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Data
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon