CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A machine shop processes custom orders from variety of clients. A machining centre in a job shop for a local manufacturing company has five unprocessed jobs remaining at a particular point in time. The jobs are labeled J1,J2,J3,J4 and J5 in the order they entered the shop. The respective processing times and due dates are given in the table below:

Job Processing
time (in days)
Due date (in days)
J1 13 65
J2 32 48
J3 34 34
J4 4 36
J5 5 35

When the jobs are assumed to enter the shop in the sequence of SPT (shortest Processing Time), the mean flow time and average tardiness, respectively, are

A
41.4 and 15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
39.4 and 14
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
35.4 and 12
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
37.4 and 13
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 35.4 and 12
Shortest processing time (SPT) rule

J4J5J1J2J3
Job
(J)
Processing
time (tj)
Flow
time (fj)
Due
date (dJ)
Lateness
(LJ)
Tardiness
(TJ)
J4 4 4 36 -32 0
J5 5 9 35 -26 0
J1 13 22 65 -43 0
J2 32 54 48 6 6
J3 34 88 34 54 54
FJ=177 TJ=60

Mean flow time, ¯Fm=1775=35.4

Average Tardiness,

¯T=TJn=605=12

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Physical Pendulum
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon