Question

A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is

  1. 14

Open in App
Solution

The correct option is A 14


Critical path = 1 - 2 - 4 - 7 - 9 - 11 - 12 = 19 days

The latest finish time (in days) for node 10 is 14 days.

Points to Remember:

The latest finish time is calculated as,

Li=[LitijE]