CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is

  1. 14

Open in App
Solution

The correct option is A 14


Critical path = 1 - 2 - 4 - 7 - 9 - 11 - 12 = 19 days

The latest finish time (in days) for node 10 is 14 days.

Points to Remember:

The latest finish time is calculated as,

Li=[LitijE]

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The Production Function
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon