Question

A project consists of activities A to M shown in the net in the following figure with the duration of the activities marked in days


The project can be completed

A
between 24, 26 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
between 60, 70 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
between 20, 22 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
between 18, 19 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A between 24, 26 days
Given network diagram as:


Maximum time along path CFKM.

So this is the critical path.

The project can be completed along C - F - K - M

= 4 + 9 + 3 + 8 = 24 days

flag
Suggest Corrections
thumbs-up
2
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to e-Business
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon