Question

A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
Activity Immediate predecessor Estimated duration (weeks)
P - 5
Q - 1
R Q 2
S P, R 4
T P 6
U S, T 3

If all the activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is
  1. 6

Open in App
Solution

The correct option is A 6


Hence different paths are:

P - T - U = 5 + 6 + 3 = 14 weeks Critical path

P - Dummy - S - U = 5 + 4 + 3 = 12 weeks

Q - R - S - U = 1 + 2 + 3 + 4 = 10 weeks

Only 'S' is delayed and no other activity is delayed.

So, maximum activity time for activity 'S' can be 6 weeks without delaying the project.

flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Transaction Demand for Money
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon