A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
Activity |
Immediate predecessor |
Estimated duration (weeks) |
P |
- |
5 |
Q |
- |
1 |
R |
Q |
2 |
S |
P, R |
4 |
T |
P |
6 |
U |
S, T |
3 |
If all the activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is
- 6