Question

A project has four activities P, Q, R and S as shown below.
Activity Normal duration (days) Predecessor Cost slope (Rs./day)
P 3 - 500
Q 7 P 100
R 4 P 400
S 5 R 200

The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs. 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is
  1. 12500

Open in App
Solution

The correct option is A 12500
Before crashing:

TC = 10000 + 200 × 12 = Rs. 12400


Since cost slope of activity S is minimum.

So, activity S will be crashed by 2 days.

1st Crashing:

TC=12400200×2overhead cost+200×2crashing cost
=Rs.12400

2nd crashing:

From various combinations/options, we get, least cost slope in Q + S activity

Crashing, Q and S by 1 day each

TC = 12400 - 1 × 200 + 1 × 300

=Rs.12500

flag
Suggest Corrections
thumbs-up
1
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Staying in Business vs Shutting Down
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon