A project has four activities P, Q, R and S as shown below.
Activity |
Normal duration (days) |
Predecessor |
Cost slope (Rs./day) |
P |
3 |
- |
500 |
Q |
7 |
P |
100 |
R |
4 |
P |
400 |
S |
5 |
R |
200 |
The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs. 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is
- 12500