Question

A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
Activity Immediate predecessor Duration (days)
A - 4
B A 3
C A 7
D B 14
E C 4
F D, E 9

The minimum project completion time (in days) is
  1. 30

Open in App
Solution

The correct option is A 30

There are two path,

A - B - D - F = 30 days

A - C - E - F = 24 days

Critical path A-B-D-F and of 30 days.

it is also the minimum time required to complete a project.