A set of jobs A, B, C, D, E, F, G, H arrive at time t = 0 for processing on turning and grinding machines. Each jobs needs to be processed in sequence-first on the turning machine and second on the grinding machine, and the grinding must occur immediately after turning. The processing times of the jobs are given by
Job | A | B | C | D | E | F | G | H |
Turning (minutes) | 2 | 4 | 8 | 9 | 7 | 6 | 5 | 10 |
Grinding (minutes) | 6 | 1 | 3 | 7 | 9 | 5 | 2 | 4 |