A takes 10 days less than the time taken by B to finish a piece of work If both A and B together can finish the work in 12 days the time taken by B to finish the work is
A
20 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
30 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
40 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
50 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A 30 days Let B alone finish the work =xdays. And Alone finish the work =(x−10)days A' s one day work =1x−10 B's one day work =1x As it given tha (A+B) can finish work in 12 days ∴(A+B)onedaywork=112 ⇒A′sonedaywork+B′sonedaywork=112 ⇒1x−10+1x=112 ⇒x+x−10x(x−10)=112 ⇒2x−10x(x−10)=112 ⇒12(2x−10)=x(x−10) ⇒24x−120=x2−10x ⇒x2−10x−24x+120=0 ⇒x2−34x+120=0 ⇒x2−30x−4x+120=0 ⇒x(x−30)−4(x−30)=0 ⇒(x−4)(x−30)=0 ⇒x=4orx=30 x≠4 ∵ifx=4thenAalonecanfinishtheworkin=(4−10)=−6dayswhichisnotpossible ∴x=30days B alone can finish work in 30 days