A takes 10 days than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.

Open in App
Solution

Let B takes x days to complete the work. Therefore, A will take (x 10) days. 1x + 1(x 10) = 112 (x 10) + xx(x 10) = 112 2x 10x2 10x = 112 x2 10x = 12(2x 10) x2 10x = 24x 120 x2 34x + 120 = 0 x2 (30 + 4)x + 120 = 0 x2 30x 4x + 120 = 0 x(x 30) 4(x 30) = 0 (x 30)(x 4) = 0 x = 30 or x = 4Number of days to complete the work by B cannot be less than that by A; therefore, we get:x = 30Thus, B completes the work in 30 days.