A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?

Open in App
Solution

Let x be the extra number of men employed to complete the job in 7 months.
Number of men 420 x
Months 9 7

Since the number of men hired and the time required to finish the piece of work are in inverse variation, we have:420 × 9 = 7xx = 420 × 97= 540Thus, the number of extra men required to complete the job in 7 months = 540 - 420 = 120