A workforce of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men mist be employ to complete the job in 7 months?
Open in App
Solution
Men Time 4209 months x7 months As the number of workers is inversely proportional to time taken: 420×9=x×7⟹x=420×97=540 ∴ extra men needed: 540−420=120