Question

A workpiece of 100cm length and 30cm width is machined by planning operation with a feed of 0.3mm/stroke. The machine tool executes 10 double strokes per minute. The planning time for a single pass is

A
50min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
100min
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
166.6min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
333.33min
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 100min
Feed per minute=0.3×10=3mm
Time taken=3003=100min

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Planing and Slotting
PRODUCTION
Watch in App
Join BYJU'S Learning Program
CrossIcon