Activities A,B,C and D constitute a small project; their interrelationship, expected duration and standard deviation of this expected duration are shown in the figure, respectively.


With a view to improving the speed of implementation, each of B,C and D are split into three equal segments, maintaining appropriate interrelationships between A and each of these nine segments. What will be the standard deviation of the modified project duration after segmentation (to the nearest 1/10 unit)?

A
5.2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
4.6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
6.2
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
5.6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 6.2
After splitting of activities, new networking diagram will be as shown

4.5=σ2B+σ2B+σ2B4.5=3σ2BσB=(4.5)23Similarly, σC=33,σD=1.53Standard deviation of total project,σ=32+3σ2B+3σ2C+3σ2D=32+4.52+32+1.52=6.36

flag
Suggest Corrections
thumbs-up
1
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Mode for a grouped data
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon