Activities A,B,C and D constitute a small project; their interrelationship, expected duration and standard deviation of this expected duration are shown in the figure, respectively.
With a view to improving the speed of implementation, each of B,C and D are split into three equal segments, maintaining appropriate interrelationships between A and each of these nine segments. What will be the standard deviation of the modified project duration after segmentation (to the nearest 1/10 unit)?