Question

Activity P is followed by activity Q which in turn is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below:

Activity P Activity Q Activity R
Duration in days 7 6 5 8 7 6 9 8 7
Direct cost Rs 1000 12 14 15 20 23 27 40 42 45

For all the three activities taken together the minimum possible direct cost for a total duration of 21 days will be:

A
81,000
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
79,000
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
77,000
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
78,000
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 77,000
Initially
P7daysQ8daysR9days24days

Cost slope for activity P & R are 2000 and for Q is 3000
P & R=(1412)761000 & 424098×1000=2000
Q=(2320)100087=3000
Crash P & R by 1 day now project duration is 22 days now P has least cost slope (1514)651000=1000
For 21 days 15,000+20,000+42,000=77,000

flag
Suggest Corrections
thumbs-up
5
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Trade and Auxiliaries to Trade
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon