Activity P is followed by activity Q which in turn is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below:
Activity P | Activity Q | Activity R | |||||||
Duration in days | 7 | 6 | 5 | 8 | 7 | 6 | 9 | 8 | 7 |
Direct cost Rs 1000 | 12 | 14 | 15 | 20 | 23 | 27 | 40 | 42 | 45 |