Ajit can do a certain work in 24 days. Bharath can do the same work in 30 days. When Chandra joins them and they do the work together, they complete the work in 12 days. Find out the time required by Chandra to complete the work alone


A
100 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
125 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
130 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
120 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 120 days

In one day Ajit can do (10024)% of the work.

In one day Bharath can do (10030)% of the work.

Working together they can do (10024)%+(10030)%=7.5% of the work in one day.

Now when Chandra joins them, they complete the work in 12 days Ajit, Bharath and Chandra together complete (10012)% of the work in a day.

Now, Ajit and Bharath do 7.5% of the work in a day.

Ajit, Bharath and Chandra do (10012)% of the work in a day.

Chandra can do (100127.5)%=(1012)% of the work in a day.

So, to complete 100% of the work, Chandra will take [100(1012)]= 120 days. Hence option (e).

2nd method:- In 12 days ajit completes 1224 i.e 50% and Bharat completes 1230 i.e 40% , then chandra completes (10090)=10% work in 12 days. Then he will take 120 days to complete full work.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Speed-Distance-Time
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon