As per the compaction specification, a highway fill of 1.5 km length has to be compacted to 90% of Indian standard light compaction test dry density. A borrow pit available near the project site has a dry density of 1.78 g/cc at 100% compaction and a void ratio of 0.63. The volume of borrow pit material required to construct a highway fill of height 5 m and top width of 10.5 with side slope of 1V:2H is (Assume G=2.7)