Question

At a certain point in the floor of weir, the uplift pressure head due to seepage is 4.5m. If the relative density of concrete is 2.5, the minimum thickness of floor required at this point to counteract the uplift pressure is

A
1 m
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2 m
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3 m
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
4 m
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 3 m
To counter the uplift pressure at the point,
Buoyant weight of concrete = seepage force on area

(2.51)× t×1=4.5×1
t = 3 m

flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Archimedes' Principle
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon