The following parameters relate to the design of weirs on permeable foundations :

1. Scour depth 2. Exit gradient
3. Uplift pressure 4. Unbalanced head

Design of the downstream end pile of the weir depends upon

A
1 and 2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1 and 4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2 and 3
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
3 and 4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 2 and 3
The downstream vertical cut-off at the end of the pucca floor is used to prevent undermining of foundation. There are two considerations for this purpose :
(i) Uplift pressure
(ii) Safe exit gradient

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Variation of Pressure in Fluids
PHYSICS
Watch in App
Join BYJU'S Learning Program
CrossIcon