The project activities, precedence relationships and durations are described in the table. The critical path of the project is
Activity | Precedence | Duration (in days) |
P | - | 3 |
Q | - | 4 |
R | P | 5 |
S | Q | 5 |
T | R, S | 7 |
U | R, S | 5 |
V | T | 2 |
W | U | 10 |