The project activities, precedence relationships and durations are described in the table. The critical path of the project is

Activity Precedence Duration (in days)
P - 3
Q - 4
R P 5
S Q 5
T R, S 7
U R, S 5
V T 2
W U 10

A
P - R - U - W
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Q - S - U - W
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
Q - S - T - V
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
P - R - T - V
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B Q - S - U - W

Possible path:

1. QSUW = 24 days critical path

2. QSTV = 18 days

3. PRTV = 17 days

4. PR VW = 23 days

flag
Suggest Corrections
thumbs-up
4
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon