Consider the following statements associated with critical path:
- Critical path is the most important sequence of activities which has no float and which determines the project completion period.
- Critical path is the largest path with shortest duration within which the project can be completed.
- The difference between early start time and late finish time must be equal to the activity duration .
Which of these statements are correct?