CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Consider the following statements associated with critical path:
  1. Critical path is the most important sequence of activities which has no float and which determines the project completion period.
  2. Critical path is the largest path with shortest duration within which the project can be completed.
  3. The difference between early start time and late finish time must be equal to the activity duration .
Which of these statements are correct?

Open in App
Solution

The duration in the critical path is the longest. However, it is the shortest duration (minimum duration) within which the project can be completed.
Since the total float and other floats are zero on the critical path.
So EST=LST and LFT=EFT and LFTEST=activity duration.

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
Join BYJU'S Learning Program
CrossIcon