wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Consider the following statements regarding PERT
1. In PERT, each activity is assumed to follow β distribution curve of time
2. Wider range in time estimates represents greater uncertainty
Which of the above statements are CORRECT ?

A
1 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Neither 1 nor 2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2 only
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Both 1 and 2
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Join BYJU'S Learning Program
CrossIcon