Embankment fill is to be compacted at a density of 18kN/m3. The soil of the borrow area is at a density of 15kN/m3.What is the estimated number of trips of 6/m3 capacity truck for hauling the soil required for compacting 100/m3 fill of the embankment? (Assume that the soil in the borrow area and that in the embankment are at the same moisture content)
V1γ1=V2γ2
For 100m fill at embankment, the volume required from borrow pit
V2=100×1815=120m3