Following data refers to activities of a project, where node 1 refers to the start and node 6 refers to the end of the project

Acitivity Duration (Days)
1-2
1-3
1-4
2-4
2-6
3-5
3-6
4-5
5-6
8
8
10
10
16
18
14
17
9

The critical path in the network is

A
1 - 2 - 4 - 5 - 6
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
1 - 3 - 5 - 6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1 - 4 - 5 - 6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1 - 2 - 6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 1 - 2 - 4 - 5 - 6

Critical path is 1 - 2 - 4 - 5 - 6.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Management Information System
BUSINESS STUDIES
Watch in App
Join BYJU'S Learning Program
CrossIcon