For a project plan activity duration and their relationship is given below:
ActivityPreceding ActivityDuration (days)A4B10CA8DA,B7EC,D9
The duration of critical path is ____ days.
  1. 26

Open in App
Solution

The correct option is A 26
The duration of critical path 1 - 3 - 4 - 5 = 26 days