For a project plan activity duration and their relationship is given below: ActivityPreceding ActivityDuration (days)A−4B−10CA8DA,B7EC,D9
The duration of critical path is ____ days.
26
Open in App
Solution
The correct option is A 26 The duration of critical path 1 - 3 - 4 - 5 = 26 days