For a work order, standard time and time taken are 20 hours and 15 hours respectively. Time rate being Rs. 2 per hour, total wages payable under Rowan's premium plan will be ________.
A
40
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
37.5
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
35
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
None of the Above
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 37.5 Rowan's Premium plan is an incentive plan. In this plan, there is a guarantee of minimum wages with the time rate but an incentive can be claimed on the basis of time saved by the worker.
In the given case, wages is calculated as:
Standard time:20 hrs
Actual Time:15 hrs
Time saved:5 hrs
Wage rate:Rs. per hour
Wages = Wage rate*Actual time + (Actual Time/Standard Time*Time saved*Rate per hour)
=(Rs.2*15)+ (Actual Time/Standard Time*Time saved*Rate per hour)