Joseph and peter can complete a work in 20 hours and 25 hours respectively. Find:
Time taken by peter to complete the remaining work.

Open in App
Solution

Time taken by joseph complete a work = 20 hours.
Time taken by peter to complete a work = 25 hours
Joseph's one hour work = 1/20
Peter's one hour work=1/25
So both joseph' and peter's work in one hour = 1/20 + 1/25
taking LCM = ( 5+ 4 )/ 100 = 9/100
work done by both together in 4 hrs = 9100×4=925
Work left after both worked together for 4 hrs =1925=(259)25=1625
Time taken by peter to complete the remaining work = 16/251/25=25×16/25 = 16 hours