CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Four jobs are to be processed on a machine as per data listed in the table.

Job Processing time (in days) Due date
1 4 6
2 7 9
3 2 19
4 8 17

If the Earliest Due Date (EDD) rule is used to sequence the jobs, the number of jobs delayed is

A
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
1
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 3
Sequence by Earliest Due Date (EDD)
Job Time Job flow time Due date Delay / Days or tardiness
1 4 0 + 4 = 4 6 +2
2 7 4 + 7 = 11 9 -2
4 8 11 + 8 = 19 17 -2
3 2 19 + 2 = 2 19 -2

No. of delay = 3

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Averages
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon