Four jobs are to be processed on a machine as per data listed in the table.
Job | Processing time (in days) | Due date |
1 | 4 | 6 |
2 | 7 | 9 |
3 | 2 | 19 |
4 | 8 | 17 |
Job | Process time | Job flow time | Due date | Days / Delays or Tardiness |
3 | 2 | 0 + 2 = 2 | 19 | 0 |
1 | 4 | 2 + 4 = 6 | 6 | 0 |
2 | 7 | 6 + 7 = 13 | 9 | 4 |
4 | 8 | 13 + 8 = 21 | 17 | 4 |