CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Four jobs are to be processed on a machine as per data listed in the table.

Job Processing time (in days) Due date
1 4 6
2 7 9
3 2 19
4 8 17

Using the Shortest Processing Time (SPT) rule, total tardiness is

A
0
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 8
Sequence by Shortest Processing Time (SPT)
Job Process time Job flow time Due date Days / Delays or Tardiness
3 2 0 + 2 = 2 19 0
1 4 2 + 4 = 6 6 0
2 7 6 + 7 = 13 9 4
4 8 13 + 8 = 21 17 4

Total tardiness = 0 + 0 + 4 + 4 = 8

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Trade, Business and Agriculture
HISTORY
Watch in App
Join BYJU'S Learning Program
CrossIcon