Question

If 100 men can complete a piece of work in 2 days, then find the time required to complete the same work by 25 men.

A
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
16 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 8 days
The number of men (N) employed to complete a piece of work is inversely proportional to the number of days (D).

N1D

Let the constant of variation be k.
N=kD
ND=k
Given, when N = 100 men , D = 2 days.
So, k=ND=(100)(2)=200
N=200D
Hence, the time required (D) to complete the same work by 25 men =20025=8 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon