Question

If 12 men and 16 boys can do piece of work in 5 days and if 13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it ?

A
323 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
813 Days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
453 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
913 Days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 813 Days
Let 1 man's 1 day's work=x
and 1 boy's 1 day's work=y
Then according to the question
12x+16y=15 and 13x+24y=14
60x+80y=1..................................................................(1)
52x+96y=1..................................................................(2)
Multiply the (1 ) by 6 and (2) by 5
360x+480y=6.............................................................(3)
260x+480y=5............................................................(4)
Add the both equation
100x=1
x=1100
put the value of x in (1) we get
60×1100+80y=1
80y=1610
80y=10610
80y=410
y=1200
(7 men+ 10 boy's 1 day's work=(7100+10200)=12100
7 Men 10 boy's do the work in 10012=813days


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
BODMAS
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon