If 18 pumps can raise 2170 tonnes of water in 10 days, working 7 hours a day then in how many days will 16 pumps raise 1736 tonnes of water, working 9 hours a day ?
A
6
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 7 Let the required number of days be x. Then, Less pumps, More days (Indirect Proportion) Less water, Less days (Direct Proportion) More hours / day, Less days (Indirect Proportion) Pumps 8 : 9 Weight 1085 : 868 Hours/day 9 : 7 :: 10 : x (8×1085×9×x)=(9×868×7×10) x=(9×868×7×10)/(8×1085×9) x=7 Answer (B) 7