If 2 men and 3 boys can do a piece of work in 10 days and 3 men and 2 boys can do it 8 days, how long will 2 men and 1 boy take to do it
A
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
18
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
12.5
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
16
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 12.5 Let men take 'm' days to complete a work and boys take 'b' days to complete the work. So in one day men do 1m job and boys do 1b job
2 men and 3 boys together do a piece of work in 10 days.Therefore we will equate job done in one day by them:
2(1m)+3(1b)=110
Similarly 3 men and 2 boys together do it in 8 days.Therefore we will equate piece of work done in one day by 3 men and 2 boys
3(1m)+2(1b)=18
Substitute 1m=p and 1b=q
So then our 2 equations becomes 2p+3q=110
and 3p+2q=18
Solving simultaneously we get p=7200 and q=2200
So we need to find number of days required to do piece of work by 2 men and 1 boy together i.e