Question
If
20
men working together can finish a job in
20
days, then find the number of day taken by
25
men of the same capacity to finish job.
Open in App
Solution
20
men working together finishes work in
20
days, If
25
men working together it would be
x
days.
So,
20
×
20
=
25
×
x
x
=
16
days
Suggest Corrections
0
Similar questions
Q.
10 men can finish a job in 10 days. In how many days 20 men can finish the same job?
Q.
If
195
men working
10
hours a day can finish a job in
20
days, how many men, working
13
hours a day, should be employed to finish the job in
15
days?
Q.
A can do a job in
10
days and B in
20
days. They work together but
4
days before the finish of the job B leaves. Find the total days to finish the job?
Q.
4 men and 6 women finish a job in 8 days while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?
Q.
Three men and 5 women together can finish a job in 3 days. Working on the same job 3 women take 5 days more than the time required by 2 men. What is the ratio of efficiency of a man to a woman?
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Time and Work
MATHEMATICS
Watch in App
Explore more
Time and Work
Standard VII Mathematics
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app