If 30 writers, writing 10 hours a day can complete a work in 15 days, then how many writers writing 8 hours a day can do double of that work in 24 days? (3 marks)
Let men required that can do double work be x.
Days | Hours | Writers |
15 | 10 | 30 |
24 | 8 | x |
We have, P1=30, D1=15, H1=10, W1=1 and P2=x, D2=24, H2=8, W2=1.
Apply formula method ,
(P1×D1×H1)/W1 =(P2×D2×H2)/W2
(1 mark)
(30×15×10)/1=(x×24×8)/1
x=(30×15×10)/(24×8)
=23.4375
= approx 23 persons
To complete the same work 23 writers needed and to complete double the work 23×2=46 writers are required.
(2 marks)