If 30 writers, writing 10 hours a day can complete a work in 15 days, then how many writers writing 8 hours a day can do double of that work in 24 days? (3 marks)


Open in App
Solution

Let men required that can do double work be x.

Days Hours Writers
15 10 30
24 8 x

We have, P1=30, D1=15, H1=10, W1=1 and P2=x, D2=24, H2=8, W2=1.

Apply formula method ,
(P1×D1×H1)/W1 =(P2×D2×H2)/W2
(1 mark)

(30×15×10)/1=(x×24×8)/1

x=(30×15×10)/(24×8)

=23.4375

= approx 23 persons

To complete the same work 23 writers needed and to complete double the work 23×2=46 writers are required.