CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
2
You visited us 2 times! Enjoying our articles? Unlock Full Access!
Question

If 36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same amount of work ?

A
24
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
36
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 24
Let 27 men complete the piece of work in x days.
Given : 36 men can complete a piece of work in 18 days.
As number of men decreases days require to complete the work will increase.
It is a case of inverse proportion.
36×18=27×x
x=36×1827=24 days

flag
Suggest Corrections
thumbs-up
34
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportion
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon