If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days the time taken by 15 men and 20 boys in doing the same type of work will be:
Open in App
Solution
Explanation : Let 1 man's 1 day's work = x and 1 boy's 1 day's work =y
Then 6x+8y =110and 26x+48y = 12
6x+8y =110 ........(1) ×6
26x+48y = 12 .........(2)
Solving these two equations we get :x=1100 and y=1200
(15men+20boy)′s1 day's work =15100+20200= 14
15 men and 20 boys can do the work in 46x+8y =110 days.