In a manufacturing company a project with six activities is going on. The three time estimates for each activity are given below.
Which of the following is the critical path for the given project?
Activitytotmtu1224623222354710563451478945456

A
12356
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
1456
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
any of the (a) and (b)
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
(a) and (b) both
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A 12356
σ2=13=0.557 days

Project duration for both parts is same but standard deviation of project for path 12356 is more.

So path 12356 will be the critical path.

Critical path = 1 - 2 - 3 - 5 - 6

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Ideal and Non Ideal Solutions
CHEMISTRY
Watch in App
Join BYJU'S Learning Program
CrossIcon