In how many days can a work be completed by A and B together? I. A alone can complete the work in 8 days. II. If A alone works for 5 days and B alone works for 6 days, the work gets completed. III. B alone can complete the work in 16 days.
A
II and either I or III
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Any two of the three
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
I and II
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
II and III
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B Any two of the three Using any two of the given statements, we can get the number of days required to complete the work by A and B separately and then we can find required number of days to complete the work with A and B working together.