CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

James can do a piece of work in 25 days and Kishan can finish it in 20 days. They work together for 5 days and then James leaves. In how many days will Kishan finish the remaining work?


A

10 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

11 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

12 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

13 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B

11 days


Time taken by James (say J) to finish the work = 25 days

J’s 1 day’s work = 125

Time taken by Kishan (say K) to finish the work = 20 days

K’s 1 day’s work = 120

(J + K)’s 1 day’s work = 125 + 120 = 9100

(J + K)’s 5 day’s work = 9×5100 = 920

Remaining work = 1 - 920 = 1120

Now, 120 work is done by K in 1 day

Therefore, 1120 work will be done by K in 11×2020 days = 11 days


flag
Suggest Corrections
thumbs-up
4
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Unitary Method for Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon