Men required to finish the work in 8 days = 10
Men required to finish the work in 1 day = 108 [More day, less men]
Men required to finish the work in half a day = = 160 [Less days, more men]
Hence, 150 (i.e., 160 − 10) men are added to finish the work in half a day.
The correct option is (d).